Category Archives: Ongoing Projects

Implementation Projects

Coastal Road Project (PR.639)

Package 2: Construction of road surface, drainage works, section Km97 + 500 – Km103 + 542.62
Place: Section Lai Giang Bridge to Thien Chanh Bridge
Representatives of investor: PMU transport Binh Dinh
Total contract value: 65,318 Billions VND
Contract duration: From Sep 2020 to Nov 2021

North –South Expressway Project section cam lo – la son

Package XL-01: Construction and Technical Design Drawings Section : Km0+000 +Km 15+000 (including bridges: Lai Phuoc, Khe Ai Tu, Over cross TL579)
Place: Cam Lo – La Son
Representatives of investor: PMU HoChiMinh road
Contract value: 547,465 Billions VND
Contract duration: From Aug 2018 to Aug 2021

Acess roads to the LONG SON Petrochemical Complex MAINTENANCE project

Package: management and maintenance of access roads to the Southern Vietnam Petrochemical Complex
Place: Ba Ria – Vung Tau Province
Representatives of investor: Long Son Petrochemicals Co., LTD
Contract duration: From Aug 2020 to Feb 2023

NH56 – Bypassing road avoiding urban zone of Ba Ria – Vung Tau province

Package 17: Construction of Road section: from Km9+800 -:- Km11+080
Place: Tanhai commune, Phu My Town, Ba Ria – Vung Tau province
Representatives of investor: PMU Cai Mep – Thi Vai
Contract duration: From Aug 2020 to Jan 2021