Construction of Cement-reinforced Treated Base (CTB) of Package XL-01 at Cam Lo – La Son section of the Eastern Expressway Project – A highlight milestone marking the efforts of the Project’s Investor and Contractors to celebrate the election day of the 15th National Assembly and People’s Council Community at all levels for the 2021-2026 term. (Source: baogiaothong.vn)

By the middle of May, 2021, the XL-01 package for the Cam Lo – La Son section basically meets the project schedule. The completed quantity is about 60%. (Source: baogiaothong.com)
Pilot Implementing the cement-reinforced treated base layer (CTB) at the site (source: baogiaothong.vn)
Construction of cement-reinforced treated base (CTB) layer is complicated, requiring high construction technology, especially for the maintenance work after compacting by rollers under hard weather in Quang Tri province. (Source: baogiaothong.vn)
Implementing the maintenance works after compaction by rollers (Source: baogiaothong.vn)
A corner of Plant for mixing the Cement-reinforced Treated Base (Source: baogiaothong.vn)